Olney Avenue connects to schools, parks, trails, businesses and more — places that kids, parents, commuters and others in the City traveling east to west need to reach. But it’s a tough stretch to safely travel when walking, biking or rolling (i.e., using a wheelchair or other mobility device) — which also makes it a stressful route to drive.

Project Updates

  • NE Olney Avenue (between NW Wall Street and NE First Street) is anticipated to remain closed through January 2026. The timeline for completing work in this area depends on the schedule of BNSF Railway, which recently shared an updated plan extending into January. The City is actively coordinating with BNSF Railway and doing everything possible to support the completion of their work at the railroad tracks as soon as possible.

    Because final paving, striping, and landscaping require warmer weather, these finishing project touches can’t be completed until spring 2026. In the meantime, the City is coordinating with BNSF Railway to allow a temporary full reopening of the roadway from late January to April 2026 using temporary pavement. A two-week full closure is expected in April 2026 to complete final paving and striping.

  • NE Olney Avenue (between NE First Street and NE Second Street) will remain closed through November 2025, with reopening anticipated in early December 2025.

We have heard the frustrations caused by the road construction projects happening around the City of Bend. We understand those frustrations and want to help answer your questions.

How to navigate new protected intersections like Olney-Wall?
Alternative Routes
What work is taking place on Olney Avenue?
Why did the City of Bend do the Greenwood Avenue Project before the Olney Avenue and Wall Street project?
Can we just make Greenwood Avenue two lanes in each direction again?
What is being done to minimize traffic impacts during construction?

SIGN UP TO RECEIVE PROJECT EMAIL UPDATES

Location

Portland Avenue to Olney Avenue starting at the Deschutes River bridge through Wall Street, 1st Street, and ending at 2nd Street.

Public Meetings

Pre-Construction Open House - January 2025
Frequently Asked Questions
April 2024 Final Design Open House
July 2023 Alternatives Analysis Open House and Survey

Background

Olney Avenue was previously identified in the City’s community-driven TSP update undertaken between 2018- 2020 as a key walking and bicycling route. The TSP was adopted by Bend City Council and projects from the TSP were included in the transportation general obligation (GO) bond passed by Bend voters in November 2020. In 2021, this project was highly prioritized by the Transportation Bond Oversight Committee.

This project combines several Transportation System Plan (TSP) projects aiming to increase safety along Olney Avenue by:

  • Creating a safer crossing at NE Second Street
  • Putting dedicated bike facilities under US 97
  • Installing dedicated user intersection safety improvements at Wall Street
  • Building a low stress, safer route for people walking and biking from the Deschutes River to NE Second Street

Synergy Improvements

To increase efficiency, save money and reduce construction impacts, water and sewer project work will be completed during the Olney construction.

  • Waterline work is essential to replace cast iron pipe installed in the 1950-70s and prevent future pipe ruptures.
  • Sewer improvements are identified as a project in the City’s 2014 Wastewater Collection System Master Plan to replace and upsize existing pipe segments to support Bend’s growth.
  • On Portland Avenue between the Deschutes River and Wall Street, some improvements from the GO Bond's Portland Avenue Corridor Improvements project and Awbrey Butte Waterline Improvement project are being included with the Olney Pedestrian and Bicycle Improvements project construction.

Funding

The Olney Project is funded by the Stormwater, Water, Water Reclamation (Sewer), Transportation and 2020 Transportation GO Bond Capital Improvement programs. The total project funding is $17 million; approximately $6 million is for utility and surface improvements at the at-grade railroad crossing on Olney Avenue.

Visit the GO Bond Dashboard for the latest budget information for this and other GO Bond projects.