City of Bend
Home MenuOlney Avenue Improvements Project
Detour Map for November through January (above)
Construction on Olney Avenue east of Wall Street to Second Street will continue through early 2026 to complete water line improvements replacing aging lines from the 1950s and increasing the water system’s durability and flexibility for emergency response. Ongoing coordination between the City and BNSF Railway continues for completing the project work and temporarily reopening the road in January.
We understand the importance of reopening Olney Avenue and appreciate the public’s patience. We will continue to provide updates as more information becomes available.
This project is replacing aging water and sewer infrastructure, and will also make it a safer road to drive, walk, bike and roll.
UpdatesLocationPublic MeetingsScheduleBackgroundFundingRelated Projects
Olney Avenue connects to schools, parks, trails, businesses and more — places that kids, parents, commuters and others in the City traveling east to west need to reach. But it’s a tough stretch to safely travel when walking, biking or rolling (i.e., using a wheelchair or other mobility device) — which also makes it a stressful route to drive.
Project Updates
- NE Olney Avenue (between NW Wall Street and NE First Street) is anticipated to remain closed through January 2026. The timeline for completing work in this area depends on the schedule of BNSF Railway, which recently shared an updated plan extending into January. The City is actively coordinating with BNSF Railway and doing everything possible to support the completion of their work at the railroad tracks as soon as possible.
Because final paving, striping, and landscaping require warmer weather, these finishing project touches can’t be completed until spring 2026. In the meantime, the City is coordinating with BNSF Railway to allow a temporary full reopening of the roadway from late January to April 2026 using temporary pavement. A two-week full closure is expected in April 2026 to complete final paving and striping.
- NE Olney Avenue (between NE First Street and NE Second Street) will remain closed through November 2025, with reopening anticipated in early December 2025.
We have heard the frustrations caused by the road construction projects happening around the City of Bend. We understand those frustrations and want to help answer your questions.
- 11/07/2025 11:00 AM
Olney Improvements Project Update -November 7, 2025
- 10/20/2025 1:00 PM
Olney Improvements Project Update - October 20, 2025
- 07/16/2025 8:00 AM
Olney Improvements Project Update - July 15, 2025
- 06/18/2025 8:00 AM
Olney Improvements Project Update - June 18, 2025
- 05/23/2025 4:30 PM
Olney Pedestrian and Bicycle Improvements Project Update - May 23, 2025
- 05/19/2025 4:00 PM
Olney Pedestrian and Bicycle Improvements Project Update - May 19, 2025
- 04/29/2025 9:00 AM
Olney Improvements Project Construction Update - April 29, 2025
- 04/10/2025 1:00 PM
Olney Pedestrian and Bicycle Improvements Project Biweekly Construction Update - April 10, 2025
- 03/28/2025 12:30 PM
Olney Avenue Project Update - March 28, 2025
- 03/13/2025 7:30 AM
Olney Avenue Weekly Construction Update - March 13, 2025
- 03/06/2025 10:17 AM
Olney Project "Coffee with the Contractor" Invitation
- 01/31/2025 4:00 PM
Olney-Wall Closure Begins Monday, Feb. 3
- 01/24/2025 10:00 AM
Olney Construction Coming Soon
- 01/09/2025 9:30 AM
Olney Pre-construction Open House Jan. 14
Location
Portland Avenue to Olney Avenue starting at the Deschutes River bridge through Wall Street, 1st Street, and ending at 2nd Street.
Public Meetings
Background
Olney Avenue was previously identified in the City’s community-driven TSP update undertaken between 2018- 2020 as a key walking and bicycling route. The TSP was adopted by Bend City Council and projects from the TSP were included in the transportation general obligation (GO) bond passed by Bend voters in November 2020. In 2021, this project was highly prioritized by the Transportation Bond Oversight Committee.
This project combines several Transportation System Plan (TSP) projects aiming to increase safety along Olney Avenue by:
- Creating a safer crossing at NE Second Street
- Putting dedicated bike facilities under US 97
- Installing dedicated user intersection safety improvements at Wall Street
- Building a low stress, safer route for people walking and biking from the Deschutes River to NE Second Street
Synergy Improvements
To increase efficiency, save money and reduce construction impacts, water and sewer project work will be completed during the Olney construction.
- Waterline work is essential to replace cast iron pipe installed in the 1950-70s and prevent future pipe ruptures.
- Sewer improvements are identified as a project in the City’s 2014 Wastewater Collection System Master Plan to replace and upsize existing pipe segments to support Bend’s growth.
- On Portland Avenue between the Deschutes River and Wall Street, some improvements from the GO Bond's Portland Avenue Corridor Improvements project and Awbrey Butte Waterline Improvement project are being included with the Olney Pedestrian and Bicycle Improvements project construction.
Funding
The Olney Project is funded by the Stormwater, Water, Water Reclamation (Sewer), Transportation and 2020 Transportation GO Bond Capital Improvement programs. The total project funding is $17 million; approximately $6 million is for utility and surface improvements at the at-grade railroad crossing on Olney Avenue.
Visit the GO Bond Dashboard for the latest budget information for this and other GO Bond projects.
