Project Status

Plan
Design
Build
Complete

Estimated Completion

To Be Determined

Contact

Drone shot of east Bend showing Pilot Butte in the distance

Franklin Avenue


PHASE 2 UPDATE – Additional Closure Scheduled Sept. 1-3 for Paving Work

  • Tuesday, Sept. 1 – Paving on Franklin Avenue from Third Street to Fourth Street
    Requires eastbound traffic closure (7 a.m. to 7 p.m.)
  • Wednesday, Sept. 2 – Paving on South side of Franklin Avenue from Fourth Street to Eighth Street
    Requires eastbound traffic closure (7 a.m. to 7 p.m.)
  • Thursday, Sept. 3 – Paving North side of Franklin Avenue from Fourth Street to Eighth Street
    Requires westbound traffic closure (7 a.m. to 7 p.m.)
  • A detour will be in place on NE Third Street, Greenwood Avenue, and NE Eighth Street.

    After paving, eastbound closure continues

    • EASTBOUND CLOSURE: Franklin Avenue from Third Street to Fourth Street, one-way westbound travel only
    • START DATE: Monday, August 17
    • DETOUR ROUTE: Third Street to Greenwood Avenue to Eighth Street

    Westbound Closure Continues

    • WESTBOUND CLOSURE: Franklin Avenue from Second Street to Third Street, one-way eastbound travel only
    • START DATE: Monday, August 3
    • DETOUR ROUTE: Third Street, Greenwood Avenue, and Wall Street

    Traffic patterns will change frequently on Franklin through mid-September – sign up for the weekly road report at bendoregon.gov/traffic.

    JOIN US FOR COFFEE WITH THE CONTRACTOR – SEPT 1

    Stop by to ask questions and learn more about the upcoming temporary closure of the Franklin Avenue underpass.

    • Tuesday, September 1
    • 8:00-10:00 a.m.
    • 182 NE Franklin Avenue in Parking Lot – enter from Second Street

    MORE SCHEDULE INFO AND DETOUR MAP BELOW

    Dates are estimates and subject to change.