North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE


SIGN UP FOR PROJECT UPDATE NOTIFICATIONS

Please correct the field(s) marked in red below:

1
Name
Name
2
Email Address
 *
  1. To receive a copy of your submission, please fill out your email address below and submit.
    CAPTCHA
    Change the CAPTCHA codeSpeak the CAPTCHA code
     

    SCHEDULE

    Summer 2019 Begin Construction
    July 2, 2019 Preconstruction Open House
    July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
    July 2019 - May 2020 Sewer Pipeline Construction
    November 2019 - March 2020 North Unit Main Canal Crossing Construction
    Fall 2020 Anticipated Project Completion