Contact

Events

More »

North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Overall Project Map with Schedule Overview

 

 

The North Interceptor Sewer Line Project is a large diameter sewer transmission line that provides additional capacity to the City’s existing sewer infrastructure, replaces portions of existing sewer infrastructure in need of repair, and gives the City the ability to decommission several regional pump stations on the north side of the City, which reduces future ongoing operational costs.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction is progressing west, and work includes excavation and installation of pipe at the North Unit Irrigation District Canal.  The project team is working to establish the preferred alignment of the Phase 2 sewer line. For more detail, see the "Project Update" section below. Additional information regarding the Juniper Ridge Construction Zone, including Frequently Asked Questions, can be found here.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.

Aerial photogragh of the North Interceptor Sewer Line canal excavation looking north.


PROJECT UPDATE


SIGN UP FOR PROJECT UPDATE NOTIFICATIONS

Please correct the field(s) marked in red below:

1
Name
Name
2
Email Address
 *
  1. To receive a copy of your submission, please fill out your email address below and submit.
    CAPTCHA
    Change the CAPTCHA codeSpeak the CAPTCHA code
     

    SCHEDULE

    Summer 2019 Begin Construction
    July 2, 2019 Preconstruction Open House
    Summer 2019 - Fall 2020 Phase 1 Construction
    Fall 2019 - Summer 2020 Phase 2 Design
    Spring 2020 - Spring 2022 Phase 2 Construction
    TBD Phase 3
    Footer Broken Top Three Sisters