Contact

Events

North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

  • October Project Update

    10/01/2019 4:33 PM

  • Construction Update - September 5th 2019

    09/05/2019 3:17 PM

  • Public Notice of Construction - August 2019

    Please be advised that construction of the North Interceptor Sewer Line Project is anticipated to begin in your neighborhood the week of August 26, 2019.

    08/22/2019 11:04 AM

  • Construction has Commenced

    Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility. In August 2019, construction will include installation of erosion control and work zone delineation, as well as excavation and installation of the pipeline between the WRF & Gentry Loop.

    07/30/2019 2:38 PM

  • Open House Rescheduled - July Project Update

    The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations and increase sanitary sewer capacity as part of the Community-supported Growth Plan. The sewer line will provide sewer conveyance to serve both developed and undeveloped la

    06/26/2019 3:53 PM

  • Open House Canceled

    05/23/2019 2:44 PM

  • Open House Info & May Project Update

    Meet the project and construction team, ask questions and learn about project plans, construction timelines, and impacts to surrounding neighborhoods.

    05/07/2019 2:34 PM

  • April Project Update

    Construction of the North Interceptor Sewer Line is expected to begin in late June or early July and last approximately 12 months

    04/09/2019 8:34 AM

  • March Update & Postcard Mailer

    The City of Bend has identified the alignment for Phase 1 of the North Interceptor Sewer Line Project and is working to obtain required easements.

    02/28/2019 3:49 PM

  • Current Activities & Preliminary Schedule

    Crews are continuing survey and preliminary design work in the project area.

    11/19/2018 10:01 AM


SIGN UP FOR PROJECT UPDATE NOTIFICATIONS

Please correct the field(s) marked in red below:

1
Name
Name
2
Email Address
 *
  1. To receive a copy of your submission, please fill out your email address below and submit.
    CAPTCHA
    Change the CAPTCHA codeSpeak the CAPTCHA code
     

    SCHEDULE

    Summer 2019 Begin Construction
    July 2, 2019 Preconstruction Open House
    July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
    July 2019 - May 2020 Sewer Pipeline Construction
    November 2019 - March 2020 North Unit Main Canal Crossing Construction
    Fall 2020 Anticipated Project Completion
    Footer Broken Top Three Sisters