Contact

Events

More »

14th Street Reconstruction Project (GO Bond)

Print
Press Enter to show all options, press Tab go to next option

14th Street construction is underway to increase safety and mobility for all users and create an environment for walking, biking and transit use.


Detour icon.

DETOURS
Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

The 14th Street Reconstruction Project is the eighth and final project funded by the voter approved transportation improvement general obligation bond. The bond initially identified the project limits between Simpson and Galveston, however City Council approved the extension for design to Newport Ave (north), and Donovan Ave (south). Funding has been allocated for Simpson to Albany (Zone 2), and Newport to Galveston (Zone 4), to be constructed as Phase 1 between April and September 2018.

PROPOSED IMPROVEMENTS

The project has divided the corridor into differing location and character. View the proposed typical sections for each zone:

Map showing NW 14th Street/SW Century Dr construction between SW Colorado Ave and SW Simpson Ave.

ZONE 1:
Colorado Ave
to Simpson Ave
Map showing NW 14th Street/SW Century Dr construction between SW Simpson Ave and NW Albany Ave.

ZONE 2:
Simpson Ave
to Albany Ave
Map showing NW 14th Street/SW Century Dr construction between NW Albany Ave and NW Galveston Ave.

ZONE 3:
Albany Ave
to Galveston Ave
Map showing NW 14th Street/SW Century Dr construction between NW Galveston Ave and NW Newport Ave.

ZONE 4:
Galveston Ave
to Newport Ave

DETOURS

Detour map showing complete closure of 14th Street between Newport Avenue and Galveston Avenue. Southbound detour involves traveling west on Newport Avenue/Shevlin Park Road, South on Mt Washington Drive, east on Skyliners Road/Galveston Ave to meet back up with 14th Street. The northbound detour is the reverse. Detour will remain in effect until early September.

View/download a printable version of the map above


PROJECT UPDATES

Photo Below:  Prepped for paving next week

 

 

Photo Below:  Early morning view of the completed segment between NW Albany Av and SW Simpson Av.  Please note, the street tree installation will begin later this fall during better plant establishment conditions

 

Photo Below: Three months ago

  • Remaining Project Schedule Highlights

    8/10/18 Week of August 13th: Paving crews will be on-site between Newport Av and Galveston Av beginning Monday morning, August 13th. Paving and striping activities will take place throughout the week with the re-opening currently scheduled for end of day, Friday the 17t

    08/10/2018 3:36 PM

  • Project Update

    8/3/18 - Open House Reminder: The City of Bend will host an open house at the Westside Village Magnet School, 1101 NW 12th Street, Monday evening August 6, from 5:30 – 7 pm. Information and graphics will be presented regarding Phase 2 construction of 14th Street, the segment between NW Galveston A

    08/03/2018 4:35 PM

  • Project Update

    Open House Reminder: The City of Bend will host an open house at the Westside Village Magnet School, 1101 NW 12th Street, Monday evening August 6, from 5:30 – 7 pm. Information and graphics will be presented regarding Phase 2 construction of 14th Street, the segment between NW Galveston Av and NW

    07/27/2018 5:36 PM

  • Project Update

    The City will be hosting an open house on August 6, from 5:30 to 7pm at the Westside Village School, 1101 NW 12th Street.

    07/24/2018 9:17 AM

  • Project Update

    14th Street reconstruction work is well underway the segment between Galveston Av and Newport Av. The complete closure of this segment requires renewed driver awareness of the designated detours. Residential areas are our safety focus as traffic patterns continue to change. The contractor’s intent

    07/11/2018 4:12 PM

  • Project Update

    July 2, 2018, SCHEDULE CHANGE: 14th Street reconstruction work has shifted to the segment between Galveston Av and Newport Av. The complete closure of this segment is now scheduled to begin Monday July 2.

    07/02/2018 2:40 PM

  • Project Updates

    June 22, 2018 Final lift paving along the entire 14th Street corridor between Simpson Av and Albany Av is still on schedule for night time work beginning Sunday night June 24th. Striping will follow the next few nights. Late night delays should be expected.

    06/26/2018 3:26 PM

  • Project Updates

    Work on Albany/14th Street has begun. The Albany/14th Street intersection work is scheduled to be completed next Friday, June 22. Final lift paving is scheduled for night time work beginning June 25th.

    06/15/2018

  • Project Updates

    Please attend the Open House on June 5 for more information. Meeting Date: Tuesday, June 5th, 5:00 – 6:30 pm Rosie Bareis Community Campus, 1010 NW 14th Street

    06/10/2018

  • Project Updates

    May 25, 2018 Access to Knoll Avenue businesses between 14th and 15th Street is currently from 15th Street; this is while crews work on waterline replacements and improvements on Knoll Avenue and the intersection.

    05/25/2018 5:53 PM

  • Project Updates

    May 17, 2018 Access to Knoll Avenue Businesses between 14th Street and 15th Street is currently from 15th Street, while crews work on waterline replacements and improvements on Knoll Avenue and the intersection

    05/22/2018

Please correct the field(s) marked in red below:

1
Name
Name
2
Email Address
 *
  1. To receive a copy of your submission, please fill out your email address below and submit.

    CONSTRUCTION SCHEDULE

    CENTURY DRIVE  - SIMPSON TO ALBANY

    Fall 2018

    Tree planting

     

    14TH STREET - GALVESTON TO NEWPORT

    July 2 – July 30

    14th Street from Galveston to Newport, Full closure of roadway for construction.

    July 31 – August 3

    Closure of the Southeast quadrant of the Newport Avenue Roundabout at 14th Street.  Detours in place for Newport eastbound traffic.

    July 31 – August 5

    14th Street from Galveston to Newport, southbound lane reopens temporarily, northbound lane remains closed.

    August 6 – August 18

    14th Street from Galveston to Newport, Full closure of roadway for construction.

     August 19 – September 28 14th Street form Galveston to Newport, road reopens, various minor components of work remain under construction with intermittent flagging and minor delays.

     

    14TH STREET – ALBANY TO GALVESTON

    August 6 – August 19

    Flagging for waterline crossing work, expect delays.

    August 20 – September 3

    14th Street from Albany Ave to Galveston Ave, east side (northbound lane) of roadway closed for construction.

    September 4 – October 31

    14thStreet from Albany Ave to Galveston Ave, Full closure of roadway for construction.

    PROJECT BACKGROUND

    In 2016 project team staff presented a GO Bond program update to City Council, requesting authority to proceed with the 14th Street Reconstruction Project, this is the eighth and final GO Bond project. Staff also proposed the extension of project limits due to lacking connectivity, sub-par infrastructure condition, transit planning efforts, recent development, updated City planning efforts, etc. City council provided authority during the January 20, 2016 meeting and requested staff present 30% level design and estimates upon completion.

    Project limits extended north and south to include the following roadway segments:

    • NW 14th Street (NW Galveston Avenue to NW Newport Avenue)
    • SW Century Drive (SW Colorado Avenue to SW Simpson Avenue)

    Project team staff presented the 30% design and project estimates to City council during the December 7, 2016 meeting. The presentation and council discussion focused on existing conditions, proposed improvements, class 4 estimates( feasibility/study phase), funding, and next steps. Next steps outlined a proposal to finalize design and outlined the estimated design fee range, schedule and funding sources. City Council voiced support for continuing to final design for the entire length of the corridor, SW Colorado Ave to NW Newport Ave. Project team staff informed City Council that they would return with a contract amendment, including scope and fee, to complete the design.


    PROJECT GOALS AND OBJECTIVES

    Project goals for the 14th Street improvements have been identified below:

    • Increase safety and mobility for all users and create an environment for walking, biking and transit use.
    • Improve accessibility by removing or providing clearance from obstructions in the sidewalk.
    • Improvements result in a more complete street with the CWP preferred land use scenario. The CWP land use scenario proposes a mixed use land use form that is projected to increase walking, biking, and transit trips thereby reducing vehicle miles traveled.

    ZONE 1 - Colorado to Simpson (in Phase II of the construction schedule) 

    Zone 1 typical section diagram: 14th Street from Colorado Avenue to Simpson Avenue.

    The proposed Zone 1 typical section extends from the intersection of SW Colorado Avenue to SW Simpson Avenue. The depiction of the typical section includes a three lane section with two way turn lane, 2 - 11 foot travel lanes, 2 - 7 foot buffered bike lanes, planter strips, and a 8 to 10 foot sidewalk on each side of the corridor. (100% Design Exhibit)

    ZONE 2 - Simpson to Albany (in Phase I of the construction schedule) 

    Zone 2 typical section diagram: 14th Street from Simpson Avenue to Albany Avenue.

    The proposed Zone 2 typical section extends from the intersection of SW Simpson Avenue to NW Albany Ave. The depiction of the typical section includes a three lane section with two way turn lane, 2 – 10.5 foot travel lanes, 2 - 7 foot buffered bike lanes, planter strips, and a 8 to 10 foot sidewalk on each side of the corridor.

    (100% Design Exhibit)

    ZONE 3 - Albany to Galveston (in Phase II of the construction schedule) 

    Zones 3 typical section diagram: 14th Street from Albany Avenue to Galveston Avenue.

    The proposed Zone 3 typical section extends from the intersection of NW Albany Avenue to NW Galveston Avenue. The depiction of the typical section includes a two lane section with 2 – 10.5 foot travel lanes, 2 - 7 foot buffered bike lanes, planter strips, and a 6 foot sidewalk on each side of the corridor.

    (100% Design Exhibit)

    ZONE 4 - Galveston to Newport (in Phase I of the construction schedule) 

    Zones 4 typical section diagram: 14th Street from Galveston Avenue to Newport Avenue.

    The proposed Zone 4 typical section extends from the intersection of NW Galveston Avenue to NW Newport Avenue. The depiction of the typical section includes a two lane section with 2 – 10.5 foot travel lanes, 2 - 7 foot buffered bike lanes, planter strips, and a 6 foot sidewalk on each side of the corridor.

    (100% Design Exhibit)

    Footer Broken Top Three Sisters

    Free viewers are required for some of the attached documents.
    They can be downloaded by clicking on the icons below.

    Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

    If you need assistance with any document, form, etc.,
    you may request assistance from the Accessibility Program.