Desert Woods & Neighborhood Extension Projects

Print
Press Enter to show all options, press Tab go to next option
Desert Woods Main photo

This project will install gravity sewer mains to allow 143 homes to decommission their aging septic systems.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Question icon.

FAQs

The Desert Woods and Neighborhood Extension Project (NEP) is the first construction phase of the Septic to Sewer Conversion Program. This project includes installing gravity sewer mains on Desert Woods Drive, King Solomon Court, King Hezekiah Way, Greenmont Drive, 15th Street, Hollis Lane, and within the Nottingham Square Subdivision. The City will also decommission two pump stations (Nottingham No. 1 and Simplicity).

 The United States Environmental Protection Agency logoThe Oregon Department of Environmental Quality logo
This project is funded by the Clean Water State Revolving Fund (CWSRF). 


PROJECT AREA

Map of the Desert Wood and Neighborhood Extension project area.

TENTATIVE PROJECT SCHEDULE

  1. King Hezekiah Way: COMPLETE
  2. Desert Woods Drive (from Orion Drive to Greenmont Drive):  COMPLETE
  3. Desert Woods Drive (from Greenmont Drive to 15th Street): IN CONSTRUCTION - Spring/Summer 2020
  4. King Solomon Court:  IN CONSTRUCTION - Spring/Summer 2020
  5. 15th Street:  Summer/Fall 2020
  6. Hollis Lane:  Summer/Fall 2020
  7. Nottingham Square Subdivision/King Richard Court:  Summer/Fall 2020
  8. Greenmont Drive: Spring/Fall/Winter 2020


PROJECT UPDATES

Desert Woods Drive and King Hezekiah Way - Segment 1 (COMPLETE)

Segment 1, located on a portion of Desert Woods Drive and King Hezekiah Way, pictured below, is substantially complete.  Property owners on Segment 1 were issued a Notice of Operational Completion (NOC) in the mail on April 27, 2020. Property owners can connect to public sewer.

Desert Woods Drive - Segment 2 (IN CONSTRUCTION)

Segment 2, located on Desert Woods Drive between Greenmont Drive and 15th Street, pictured below, is in construction and anticipated to be complete by mid-June 2020. For information regarding schedule, traffic detours, and what to expect during construction, see the Segment 2 Construction Facts Sheet.

Property owners on Segment 2 will be issued a Notice of Operational Completion (NOC) in the mail when the sewer is active and ready to be discharged to. Property owners will not be permitted to connect to the sewer before the City issues the NOC.

A map depicting the proposed sewer and project segment boudaries between 15th St and Greenmont Dr, and the existing Southeast Interceptor location along Orion Dr for Desert Woods Drive - Segment 2.

King Solomon Court - Segment 3 (IN CONSTRUCTION)

Segment 3, located on King Solomon Court, pictured below, is in construction and anticipated to be complete by mid-June 2020. For information regarding the schedule, traffic detours, and what to expect during construction, please see the Segment 3 Construction Facts Sheet.

Property owners on Segment 3 will be issued a Notice of Operational Completion (NOC) in the mail when the sewer is active and ready to be discharged to. Property owners will not be permitted to connect to the sewer before the City issues the NOC.

A map depicting the proposed sewer and project segment boudaries along King Solomon Ct , and the existing Southeast Interceptor location along Orion Dr for King Solomon Court - Segment 3.

Greenmont Drive - Segment 4 (IN CONSTRUCTION)

Segment 4, located on a portion of Greenmont Drive pictured below, is in construction and anticipated to be complete by mid-June 2020. For information regarding the schedule, traffic detours, and what to expect during construction, please see the Segment 4 Greenmont Drive Facts Sheet.

Property owners on Segment 4 will be issued a Notice of Operational Completion (NOC) in the mail when the sewer is active and ready to be discharged to. Property owners will not be permitted to connect to the sewer before the City issues the NOC.

 

TRAFFIC CONTROL PLAN

Effective May 4, 2020 Through Mid-June 2020

December 11, 2019 - Desert Woods and King Hezekiah Outreach

Desert Woods and King Hezekiah Outreach

Wednesday, December 11; 7-8 PM
Larkspur Center (1600 SE Reed Market)

Property owners directly affected by the upcoming first phase of the Desert Woods and Neighborhood Extension Project construction are invited to an open house to learn more about this project, scheduled to begin in January 2020.

Discussion items include:

  • What to expect during construction
  • Detours/Traffic Control
  • Tentative Notice of Operational Completion Issuance
  • Stub-out locations - locations at your home will be staked with green flagging near the right-of-way at your property in advance of this meeting. Please come prepared to discuss yours.
Return to full list >>

Expand/Contract Questions and Answers

  • 1 What are the benefits of converting to City sewer?

  • 2 When will I be required to connect to City sewer?

  • 3 How are Neighborhood Extension Projects chosen?

  • 4 How much money is available for the Septic to Sewer Conversion Projects, and what can the money be used for?

  • 5 What is the process to decommission a septic system and how much does it cost?

  • 6 After a sewer project is completed, when will I be able to connect to sewer?

  • 7 If I signed the Neighborhood Extension Project application and sell my house, does the new buyer have to connect within 2 years?

  • 8 Will I be guaranteed a gravity sewer connection?

Footer Broken Top Three Sisters

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

If you need assistance with any document, form, etc.,
you may request assistance from the Accessibility Program.