North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

October Project Update

Post Date:10/01/2019 4:33 PM

The North Interceptor Sewer Line Project is an important project that will help the City of Bend meet anticipated sewer demands. The large diameter sewer transmission line is approximately 37,000 feet in length and is divided into three distinct phases. The first phase of the project began in August of 2019 and includes work from Pioneer Loop to the City of Bend Water Reclamation Facility.

Ongoing Activities:

  • Crews are continuing drilling and blasting work as they progress west on Gentry Loop.

  • Excavation for sewer trench continues. Pipe installation along Gentry Loop is expected through the month of October.

  • Preliminary work will begin on the west side of canal as early as mid-October.  Truck traffic on Pioneer Loop is to be expected.

  • Continued work at the Water Reclamation Facility pump station includes concrete formwork and pouring.

  • Construction work across the North Unit Irrigation Canal is scheduled to begin in November. 

Scheduled work hours are Monday-Saturday from 7a.m. – 6 p.m. and occasional extended work hours as required.  No night work is currently planned. 

What to Expect During Construction:

  • Local access to all properties will be maintained, but construction may create delays.

  • Expect minor traffic shifts and flaggers on Gentry Loop during work through October.

  • The project team will maintain a haul road within the Temporary Construction Easement (TCE) for the project.

  • Safety is our utmost priority.  During blasting activities, please stay clear of the construction area and respect all project boundaries and construction personnel. Those in close proximity to the blasting will be contacted again no later than 48 hours prior to blasting. 

    • What you can expect during blasting activities:

      • Air horns leading up to the blast

      • Sounds and/or light ground vibration during the blast

      • Dust in the air that will dissipate quickly after the blast

      • Faint smell of explosive material that will dissipate quickly after the blast 

Work Zone Safety
Please be aware of the construction work zone and allow extra time to get where you’re going.  Any time you’re in or approaching a work zone, please remember to:

  • Slow Down

  • Be Kind   – our workers are out there helping to keep you safe and improve the roadways

  • Pay Attention – both to workers directing you and surrounding traffic; put down your phone when behind the wheel

  • Stay Calm – expect delays, leave early or take an alternate route if possible; no meeting or appointment is worth risking someone’s life  

If you have any specific questions or concerns, please call the project team at (541) 382-3264. 

You can learn more about the North Interceptor Sewer Line Project at bendoregon.gov/north-interceptor

Image of the installation of a 54" Sewer Pipe
Above: 54” Sewer Pipe Installation


Above: Concrete Forms for Pump Station

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion