Show/Hide

COVID-19 INFO: City closures and cancellations, resources for businesses and people.

North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option
A photo of excavation equipment excavating a pipe trench.

The North Interceptor Sewer Line Project is a large diameter sewer transmission line that provides additional capacity to the City’s existing sewer infrastructure, replaces portions of existing sewer infrastructure in need of repair, and gives the City the ability to decommission several regional pump stations on the north side of the City, which reduces future ongoing operational costs.


Information icon.

JUNIPER RIDGE
PROJECT WEBSITE
Meetings icon.

VIRTUAL
OPEN HOUSE
Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction is progressing and is on schedule to be complete in Fall 2020. For more details, see the "Project Updates" section below.

Phase 2 design is nearing completion, and construction is expected to begin in June 2020. For a more detailed map of phase two, see the Phase 2 Segments Map.

For additional information regarding the Juniper Ridge construction zone, including Frequently Asked Questions, see the Juniper Ridge Construction Plan Update & FAQs.

Para obtener información en español sobre la zona de construcción en Juniper Ridge, consulte la Actualización del plan de construcción de Juniper Ridge y preguntas frecuentes.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line at (541) 382-3264.


PROJECT LOCATION

Overall Project Map with Schedule Overview


VIRTUAL OPEN HOUSE - JOIN US ONLINE!

Beginning Wednesday, May 27, 2020, we invite you to attend our virtual open house for Phase II construction of the North Interceptor Sewer Project. To attend, please visit www.bendsewerline.com.

If you have questions about the virtual open house or issues accessing the virtual open house website, please call the 24-hour project phone line at 541-382-3264.


PROJECT UPDATES

North Interceptor Sewer Project Update - October 1, 2019

Post Date:10/01/2019 4:33 PM

The North Interceptor Sewer Line Project is an important project that will help the City of Bend meet anticipated sewer demands. The large diameter sewer transmission line is approximately 37,000 feet in length and is divided into three distinct phases. The first phase of the project began in August of 2019 and includes work from Pioneer Loop to the City of Bend Water Reclamation Facility.

Ongoing Activities:

  • Crews are continuing drilling and blasting work as they progress west on Gentry Loop.

  • Excavation for sewer trench continues. Pipe installation along Gentry Loop is expected through the month of October.

  • Preliminary work will begin on the west side of canal as early as mid-October.  Truck traffic on Pioneer Loop is to be expected.

  • Continued work at the Water Reclamation Facility pump station includes concrete formwork and pouring.

  • Construction work across the North Unit Irrigation Canal is scheduled to begin in November. 

Scheduled work hours are Monday-Saturday from 7a.m. – 6 p.m. and occasional extended work hours as required.  No night work is currently planned. 

What to Expect During Construction:

  • Local access to all properties will be maintained, but construction may create delays.

  • Expect minor traffic shifts and flaggers on Gentry Loop during work through October.

  • The project team will maintain a haul road within the Temporary Construction Easement (TCE) for the project.

  • Safety is our utmost priority.  During blasting activities, please stay clear of the construction area and respect all project boundaries and construction personnel. Those in close proximity to the blasting will be contacted again no later than 48 hours prior to blasting. 

    • What you can expect during blasting activities:

      • Air horns leading up to the blast

      • Sounds and/or light ground vibration during the blast

      • Dust in the air that will dissipate quickly after the blast

      • Faint smell of explosive material that will dissipate quickly after the blast 

Work Zone Safety
Please be aware of the construction work zone and allow extra time to get where you’re going.  Any time you’re in or approaching a work zone, please remember to:

  • Slow Down

  • Be Kind   – our workers are out there helping to keep you safe and improve the roadways

  • Pay Attention – both to workers directing you and surrounding traffic; put down your phone when behind the wheel

  • Stay Calm – expect delays, leave early or take an alternate route if possible; no meeting or appointment is worth risking someone’s life  

If you have any specific questions or concerns, please call the project team at (541) 382-3264. 

You can learn more about the North Interceptor Sewer Line Project at bendoregon.gov/north-interceptor

Image of the installation of a 54" Sewer Pipe
Above: 54” Sewer Pipe Installation


Above: Concrete Forms for Pump Station

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


PROJECT SCHEDULE

 Summer 2019  Begin Construction
 July 2, 2019  Preconstruction Open House
 Summer 2019 - Fall 2020  Phase 1 Construction
 Fall 2019 - Summer 2020  Phase 2 Design
 Spring 2020 - Spring 2022  Phase 2 Construction
 Spring 2022  Overall Phase 2 Completion
 TBD  Phase 3
Footer Broken Top Three Sisters