North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

Construction Update - September 5th 2019

Post Date:09/05/2019 3:17 PM

Current Activities:

  • 60” and 54” Interceptor pipeline has been installed east of Gentry Loop, near the Water Reclamation Facility (WRF).  Additionally, the pump station has been excavated and is ready for structural concrete work to begin.
  • Crews have also begun working on Gentry loop.  Traffic control measures are set up and drilling and blasting activities along the road are progressing through the next several weeks.  Some things to be aware of for drilling and blasting activities:
    • Safety is our utmost priority.  During blasting activities, please stay clear of the construction area and respect all project boundaries and construction personnel.
    • What you can expect during blasting activities:
      • Air horns leading up to the blast
      • Sounds and/or light ground vibration during the blast
      • Dust in the air that will dissipate quickly after the blast
      • Faint smell of explosive material that will dissipate quickly after the blast

Current scheduled work hours are Monday-Saturday from 7a.m. – 6 p.m. and occasional extended work hours as required.  No night work is currently planned.

Upcoming Milestones:

Construction across the North Unit Irrigation Canal is scheduled to begin in November of 2019.

Project Overview:

The North Interceptor Sewer Line Project is an important project that will help the City of Bend meet anticipated sewer demands. The large diameter sewer transmission line for Bend’s north side will allow the City to decommission pump stations, increase sewer capacity, and create the necessary connection for the future East Interceptor. The first phase of the project includes work from Pioneer Loop Road to the City of Bend Water Reclamation Facility.

Please relay your concerns, comments, and questions to the project team at (541) 382-3264.

 

Interceptor Pipe Installation

Above: Interceptor Pipeline Installation

 

Gentry Loop looking west

Above: Gentry Loop Looking West with Drilling Operations in the Background

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion
Footer Broken Top Three Sisters