 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

Public Notice of Construction - August 2019

Post Date:08/22/2019 11:04 AM

Please be advised that construction of the North Interceptor Sewer Line Project is anticipated to begin in your neighborhood the week of August 26, 2019. The North Interceptor Sewer Line Project is an important project that will help the City of Bend meet anticipated sewer demands. The large diameter sewer transmission line for Bend’s north side will allow the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.

The scope of work for this phase of the project includes work from Pioneer Loop Road to the City of Bend Water Reclamation Facility.  Work will include, but is not limited to, traffic control, erosion control, clearing and grubbing, drilling, blasting, excavation for and installation of sewer pipe and surface restoration.  Those in close proximity to the blasting will be contacted again no later than 48 hours prior to blasting. 

All work is scheduled to be within Deschutes County right-of-way or the temporary construction easements established for the project.  While the intent is to minimize disruptions, we thank you in advance for your patience during the construction activities.  

You may experience some traffic delays and inconveniences during this time however you will always have access to your property. We thank you for your cooperation and patience.  We also request that when driving in the vicinity of the work area, you follow and obey the construction signage for your safety and for the safety of the workers.  Please provide particular consideration to pets, property, children, and yourselves by limiting activities to only areas outside the work area.  

Our scheduled work hours are Monday-Friday from 7a.m. – 6 p.m. with the possibility of extended hours depending on work requirements.  During the course of the project, it may be necessary to work Saturday and Sunday.  In those instances, we will reach out and provide specific updates.

Should you have any questions or concerns, please don't hesitate to contact the City of Bend or our contractor, Mortenson Construction. We look forward to working with you during this important project and are available to respond to questions as needed.

Mortenson Contacts:

Tim Johnson, Project Superintendent, 480-259-8360, tim.w.johnson@mortenson.com

Steve Holmes, Project Manager, 503-400-0638, steve.holmes@mortenson.com

Ruger Harden, Project Engineer, 559-972-8733, ruger.harden@mortenson.com

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion