North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

Construction has Commenced

Post Date:07/30/2019 2:38 PM

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations and increase sanitary sewer capacity as part of the Community-supported Growth Plan. The sewer line will provide sewer conveyance to serve both developed and undeveloped lands.

The Phase 1 Preconstruction Open House was held on Tuesday, July 2, 2019. Community members had the opportunity to meet the project and construction team, ask questions and learn about project plans, construction timelines, and impacts to surrounding neighborhoods.

  • Phase 1 construction of the North Interceptor Sewer Line began in July at the Water Reclamation Facility.
  • In August, construction will include installation of erosion control and work zone delineation, as well as excavation and installation of the pipeline between the Water Reclamation Facility to Gentry Loop.
  • Blasting is scheduled to begin east of Gentry Loop on Wednesday, July 31, 2019, between 7:00 a.m. and 6 p.m. Drilling and blasting are a common means of rock excavation in the area and anticipated during construction. All property owners with structures within 300 feet of the blasting area will be contacted directly by the contractor. Preconstruction and post-construction surveys will be completed by the contractor to ensure no damage to any private property.  Please work with our contractor to gain access to your property so that this survey may be completed in the best way possible.  

Drilling Operation at WRF

Drilling Operation at WRF

 


Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion