Weekly Road and Traffic Report

Print
Press Enter to show all options, press Tab go to next option

Keep up-to-date on weekly closures and detour routes during peak construction season.


During peak construction season—typically April through October—we send out weekly road and traffic reports each Friday to help members of our community plan the quickest, safest and most reliable routes to their destinations. The weekly report is intended to provide information about various projects within City limits that impact the roadways.

 


TRAFFIC IMPACT LOCATIONS

The map below shows lane and road closures on arterials and collectors and full closures on residential streets.

Click and drag to navigate the map, or use the + or – buttons to zoom. For information about a specific, highlighted project on the map, click it and a pop-up window will appear that contains detailed information.


WEEKLY ROAD AND TRAFFIC REPORTS

Weekly Road and Traffic Report for the week of June 24-30

Post Date:06/21/2019 1:53 PM

Special Events 

  • Bend Pride 5K Run/Walk will be held on June 22 and will have flaggers at the intersection of NW Galveston Avenue and NW Riverfront Street.

  • Blitz to the Barrel will be held on June 26 and will have the following impacts:

    • Flaggers at the intersection of NW 14th Street and NW Galveston Avenue

    • NW 12th Street closed between NW Galveston Avenue and NW Fresno Avenue

  • Great Race will be held on June 27 and will close NW Wall Street between NW Newport Avenue and NW Franklin Avenue.

  • Worthy Taps & Tacos Anniversary will be held on June 30 and will close Brooks Alley between NW Franklin Avenue and Crows Feet Commons.

For the Week of June 24 – 30

  • City of Bend Residential Slurry Seal street restoration begins on the week of 6/20/19 - 6/28/19. Residents within the project areas will receive notification of dates and times for temporary street closures via reader boards and Type II Barricades. Restoration work will begin in the Aspen Rim, West Park, Forest Meadow, Quail Pine Estates, Pine Ridge Estates, and River Canyon Estates neighborhood areas.

  • Roundabout at intersection of SW Simpson Avenue and SW Colorado Avenue for pavement resurfacing, roundabout closure with detours, 6/23/19, 7 p.m. - 5 a.m.

  • SW Century Drive between Mt. Washington Drive and Skyline Ranch Road for milling and paving, lane closures with flaggers, night work from 6/23/19 - 6/27/19.

  • SW Colorado Avenue between SW Simpson Avenue and SW Industrial Way for pavement resurfacing, road closures with detours, 6/24/19 - 6/25/19, 7 p.m. - 5 a.m.

  • Brosterhous Road between Whitetail Street and Franke Lane for infrastructure installation, road closure with detour, 6/24/19 - 7/8/19.

  • Cooley Road between NE Hunnell Road and N Highway 97 for paving, road closure with detour, 6/26/19, night work from 7 p.m. - 4 a.m.

  • NW Federal Street between NW Nashville Avenue and NW Milwaukee Avenue for infrastructure installation, road closure with detour and local access only, 6/25/19 - 6/27/19.

Ongoing Closures 

  • NE 4th Street between NE Addison Avenue and NE Xerxes Avenue for infrastructure installation, road closure with detour, 6/10/19 - 7/12/19.

  • Eagle Road between NE Neff Road and NE Monte Vista Lane for infrastructure installation, northbound lane closure with detour, 6/10/19 - 6/26/19.

  • Roundabout at intersection of NW Shevlin Park Road and NW Mt. Washington Drive for roundabout reconstruction, road closure with detours, 5/13/19 - 7/3/19.

  • The intersection of Empire Avenue and Purcell Boulevard will be closed to complete the construction of a new roundabout at this intersection. The closure will begin on Monday, June 17 and will last approximately eight weeks. Access to Terrango Glen and Lava Ridges neighborhoods will be maintained during construction. Detours will be signed and a map showing these detours will be issued in future outreach efforts. Please be aware of construction speed limit changes in this area.

Upcoming Closures 

  • Powers Road between SW Elkhorn Street and Porcupine Drive for milling and paving, road closure with local access only, 7/1/19 - 7/2/19.

  • Rockbluff Lane between SW Elkhorn Street and SW Cliffrose Drive for milling and paving, road closure with local access only, 7/1/19 - 7/2/19.
  • SE 3rd Street between Murphy Road and Badger Road for bus stop installation, northbound lane shifts and center turn lane closures, 7/1/19 - 7/3/19.
  • Brosterhous Road between American Lane and News Lane for infrastructure installation, road closure with detours, 7/8/19 - 8/1/19.

  • SE White Tail Street between Brosterhous Road and Brentwood Avenue for infrastructure installation, road closure with detour, 7/8/19 - 8/1/19.

 

Work schedules are dependent on weather conditions and other factors.

 

Contact: Kyle Thomas, Construction Manager

541-323-8519, kthomas@bendoregon.gov

 

For Street Preservation related questions: Paul Neiswonger, Streets Supervisor

541-317-3035, pneiswonger@bendoregon.gov

 

Closures and detours in Bend are updated weekly at: www.bendoregon.gov/traffic

Find more information about street operations at: www.bendoregon.gov/streetpreservation

Weekly reports can be received via email by subscribing to Weekly Road and Traffic Reports at www.bendoregon.gov/enews

 

ADA wheelchair icon.Accommodation Information for People with Disabilities

To obtain this information in an alternate format such as Braille, large print, electronic formats, etc. please contact Anne Aurand at 541-388-5573 or aaurand@bendoregon.gov.

Return to full list >>
Footer Broken Top Three Sisters

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.