North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option
A photo of excavation equipment excavating a pipe trench.

The North Interceptor Sewer Line Project is a large diameter sewer transmission line that provides additional capacity to the City’s existing sewer infrastructure, replaces portions of existing sewer infrastructure in need of repair, and gives the City the ability to decommission several regional pump stations on the north side of the City, which reduces future ongoing operational costs.


Information icon.

JUNIPER RIDGE
PROJECT WEBSITE
Meetings icon.

VIRTUAL
OPEN HOUSE
Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction is progressing and is on schedule to be complete in Fall 2020. For more details, see the "Project Updates" section below.

Phase 2 design is nearing completion, and construction is expected to begin in June 2020. For a more detailed map of phase two, see the Phase 2 Segments Map.

For additional information regarding the Juniper Ridge construction zone, including Frequently Asked Questions, see the Juniper Ridge Construction Plan Update & FAQs.

Para obtener información en español sobre la zona de construcción en Juniper Ridge, consulte la Actualización del plan de construcción de Juniper Ridge y preguntas frecuentes.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line at (541) 382-3264.


PROJECT LOCATION

Overall Project Map with Schedule Overview


VIRTUAL OPEN HOUSE - JOIN US ONLINE!

Beginning Wednesday, May 27, 2020, we invite you to attend our virtual open house for Phase II construction of the North Interceptor Sewer Project. To attend, please visit www.bendsewerline.com.

If you have questions about the virtual open house or issues accessing the virtual open house website, please call the 24-hour project phone line at 541-382-3264.


PROJECT UPDATES

North Interceptor Sewer Project Update & Open House Info - May 7, 2019

Post Date:05/07/2019 2:34 PM

Project status:

  • The Guaranteed Maximum Price (GMP) contract for construction of the project will be presented to City Council on June 5, 2019. The GMP contract will establish a price for the construction of North Interceptor Sewer Line scope of work, that cannot be exceeded.
  • Preconstruction Open House

    Meet the project and construction team, ask questions and learn about project plans, construction timelines, and impacts to surrounding neighborhoods.

    Wednesday, June 12, 2019

    5:00 p.m. – 7:00 p.m.

    Buckingham Elementary School

    62560 Hamby Rd, Bend, OR

  • Construction of the North Interceptor Sewer Line is expected to begin in late June or early July of 2019 and finish in September of 2020. Details specific to the construction of the project will be provided at the open house.
Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


PROJECT SCHEDULE

 Summer 2019  Begin Construction
 July 2, 2019  Preconstruction Open House
 Summer 2019 - Fall 2020  Phase 1 Construction
 Fall 2019 - Summer 2020  Phase 2 Design
 Spring 2020 - Spring 2022  Phase 2 Construction
 Spring 2022  Overall Phase 2 Completion
 TBD  Phase 3