North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

April Project Update

Post Date:04/09/2019 8:34 AM

Project status:

  • The Guaranteed Maximum Price (GMP) contract for construction of the project is anticipated to be presented to City Council on June 5, 2019.  The GMP contract will establish a price "not to be exceeded"  for the construction of the North Interceptor Sewer Line scope of work.
  • An open house will be held before construction begins on the project (tentatively planned for early June 2019). The community will be notified of the open house via mailers and email.
  • Construction of the North Interceptor Sewer Line is expected to begin in late June or early July and last approximately 12 months. Details specific to the construction of the project will be provided at the open house and communicated throughout the duration of the project.
Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion