North Interceptor Sewer Line Project

Print
Press Enter to show all options, press Tab go to next option

 

 Interceptor Pipe Installation

 

Project Overview Map

Phase 1 Alignment Map

Alignment map button

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations, increase sewer capacity and create the necessary connection for the future East Interceptor.


Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction of the North Interceptor Sewer Line began in July 2019 at the Water Reclamation Facility.

During the month of October, crews will continue drilling and blasting work as they progress west on Gentry Loop. Work at the pump station includes concrete formwork and pouring.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line

(541) 382-3264.


PROJECT UPDATE

March Update & Postcard Mailer

Post Date:02/28/2019 3:49 PM

The City of Bend has identified the alignment for Phase 1 of the North Interceptor Sewer Line Project and is working to obtain required easements.  

The alignment runs from Pioneer Loop to the Water Reclamation Facility (WRF). The city will hold an open house before construction where city staff and consultants will be available to describe the elements of the project, including what may be expected during construction and how access to the area might be impacted. Construction is expected to begin in Summer 2019.

 

Project status:

  • Survey and geotechnical work are completed
  • Project team is working with property owners to obtain required easements

 

 The project team sent out a postcard mailer on 2/13/19. A copy of the mailer is shown below.

Copy of February Postcard

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


SCHEDULE

Summer 2019 Begin Construction
July 2, 2019 Preconstruction Open House
July 2019 - September 2019 Water Reclamation Facility Lift Station Construction
July 2019 - May 2020 Sewer Pipeline Construction
November 2019 - March 2020 North Unit Main Canal Crossing Construction
Fall 2020 Anticipated Project Completion