The North Interceptor Sewer Line Project is a large diameter sewer transmission line that provides additional capacity to the City’s existing sewer infrastructure, replaces portions of existing sewer infrastructure in need of repair, and gives the City the ability to decommission several regional pump stations on the north side of the City, which reduces future ongoing operational costs.


Information icon.

JUNIPER RIDGE
PROJECT WEBSITE
Meetings icon.

VIRTUAL
OPEN HOUSE
Construction icon.

PROJECT UPDATES
Add user icon.

SIGN UP FOR
NOTIFICATIONS
Calendar icon.

SCHEDULE

Phase 1 construction is progressing and is on schedule to be complete in Fall 2020. For more details, see the "Project Updates" section below.

Phase 2 design is nearing completion, and construction is expected to begin in June 2020. For a more detailed map of phase two, see the Phase 2 Segments Map.

For additional information regarding the Juniper Ridge construction zone, including Frequently Asked Questions, see the Juniper Ridge Construction Plan Update & FAQs.

Para obtener información en español sobre la zona de construcción en Juniper Ridge, consulte la Actualización del plan de construcción de Juniper Ridge y preguntas frecuentes.

If you have any specific questions or concerns, please don’t hesitate to call the project phone line at (541) 382-3264.


PROJECT LOCATION

Overall Project Map with Schedule Overview


VIRTUAL OPEN HOUSE - JOIN US ONLINE!

Beginning Wednesday, May 27, 2020, we invite you to attend our virtual open house for Phase II construction of the North Interceptor Sewer Project. To attend, please visit www.bendsewerline.com.

If you have questions about the virtual open house or issues accessing the virtual open house website, please call the 24-hour project phone line at 541-382-3264.


PROJECT UPDATES

North Interceptor Sewer Project Current Activities & Preliminary Schedule - November 19, 2018

Post Date:11/19/2018 10:01 AM

Current Activities  

  • Crews are continuing survey and preliminary design work in the project area.
  • The preferred alignment of the transmission line is still being determined.
  • The project team have been in contact with property owners to discuss the potential alignment of the transmission line.

Preliminary Schedule

  • Construction is expected to begin in the Spring of 2019 with the pipeline installation from the North Unit Main Canal to the Water Reclamation Facility.
  • An open house will be scheduled before work begins on the project - after the first of the year.

Thanks for relaying your concerns, comments, and questions to the project team at (541) 382-3264.

Return to full list >>

SIGN UP FOR PROJECT UPDATE NOTIFICATIONS


PROJECT SCHEDULE

 Summer 2019  Begin Construction
 July 2, 2019  Preconstruction Open House
 Summer 2019 - Fall 2020  Phase 1 Construction
 Fall 2019 - Summer 2020  Phase 2 Design
 Spring 2020 - Spring 2022  Phase 2 Construction
 Spring 2022  Overall Phase 2 Completion
 TBD  Phase 3