Weekly Road and Traffic Report

Post Date:04/27/2018 10:34 AM

Weekly Road and Traffic Report

 

For the week of:

April 30 – May 6

 

 

2018 City of Bend Street Preservation Projects (More information: www.bendoregon.gov/streetpreservation):

 

  • Brooks Street between Oregon Avenue and Newport Avenue for pavement milling, road closure with detour, 5/6/18, night work from 7 p.m. – 6 a.m.
  • Oregon Avenue/Hawthorne Avenue between Brooks Street and Highway 97 for pavement milling, road closure with detour, 5/6/18, night work from 7 p.m. – 6 a.m.
  • Ross Road between Boyd Acres Road and Hidden Valley Drive for grind and inlay paving work, eastbound lane closure with detour, 4/30/18, 7 a.m. – 4 p.m.

     

    14th Street Reconstruction Project:

     

  • The Simpson Avenue Roundabout at Century Drive is fully closed for work on the first stage of the project, which includes reconstruction of the Simpson Roundabout to a concrete surface and construction of the east side of Century Drive from Simpson Avenue to Albany Avenue.  The roundabout is expected to reopen mid-May.  Access to businesses in this area will remain open throughout construction. Google Maps and Waze will be updated with current closures due to this project. For project and detour info: www.bendoregon.gov/14thstreet
  •  

     

    Other ongoing closures:

     

  • 14th Street between Galveston Avenue and Newport Avenue for Cascade Natural Gas main relocation, southbound lane closed with detours in place, 3/26/18 – 6/8/18.
  • Brosterhous Road between Marble Mountain Lane and Orchard Grass Place, bike lane closed for road construction and curb installation, 4/2/18 – 4/30/18.

 

Work schedules are dependent on weather conditions and other factors.

 

Contact: Kyle Thomas, Construction Manager

541-323-8519, kthomas@bendoregon.gov

 